Skip to main content
Market Intelligence 7 min read

How Much BIL Funding Has Actually Reached Water Utilities?

January 28, 2026United Current Team

The Promise vs. the Pipeline

When the Bipartisan Infrastructure Law was signed in November 2021, the water sector celebrated a generational investment: $55 billion earmarked for drinking water, wastewater, and stormwater infrastructure. It was the single largest federal commitment to water systems in decades, spanning the Drinking Water State Revolving Fund (DWSRF), the Clean Water State Revolving Fund (CWSRF), and dedicated carve-outs for lead service line replacement, PFAS remediation, and emerging contaminant treatment.

Four years later, the question every vendor, utility director, and policy analyst is asking is straightforward: how much of that money has actually reached the systems that need it?

We set out to answer that question by analyzing federal award data from USASpending.gov, EPA allotment tables, and state-level SRF disbursement records. The picture that emerges is more nuanced, and in some cases more frustrating, than the headline number suggests.

What the Numbers Show

As of Q4 2025, the EPA has allotted approximately $35.2 billion of the $55 billion authorization to states through annual capitalization grants. This is the money that has left the federal ledger and landed in state SRF programs. It includes both the general supplemental funding and the dedicated set-asides for lead, PFAS, and emerging contaminants.

However, allotment is not the same as disbursement. States must then award that money to individual water systems through their Intended Use Plan (IUP) process. Our analysis of available state-level data shows that roughly $22.4 billion has been committed to specific projects through executed loan or grant agreements. That means about 64 percent of the allotted funds have been formally committed, and the remainder sits in various stages of state-level review, application processing, or reserve.

The gap between commitment and actual cash disbursement is even wider. Based on draw-down data from Treasury and state financial reports, we estimate that approximately $14.8 billion has been physically disbursed to utilities or their contractors, meaning checks have been written and work is either underway or complete. That is roughly 27 percent of the total $55 billion authorization.

State-by-State Variation Is Enormous

One of the most striking findings is the degree of variation across states. Some states have moved aggressively to deploy BIL funds, while others are still working through administrative bottlenecks.

Top performers by disbursement rate:

  • Texas has disbursed over 78% of its allotted BIL funds, benefiting from a well-staffed Water Development Board and a pre-existing pipeline of shovel-ready projects.
  • Ohio has committed nearly 85% of its allotment, aided by a streamlined application process and strong coordination between the Ohio EPA and local utilities.
  • California has committed a large absolute dollar amount but its disbursement rate sits closer to 55%, reflecting the complexity of its regulatory environment and the sheer number of small systems in the state.

States facing bottlenecks:

  • New Mexico and Mississippi have disbursement rates below 30%, driven in part by limited state administrative capacity and a large number of small, under-resourced utilities that struggle to complete applications.
  • West Virginia, despite having significant need, has faced challenges matching federal funds with local cost-share requirements, slowing the flow of dollars to communities.

These disparities matter enormously for vendors. A company selling membrane filtration systems or pipeline rehabilitation services needs to understand not just where the need is, but where the funded, approved, and moving projects are.

The SRF Bottleneck

The structural challenge is the State Revolving Fund model itself. The SRF was designed in the 1980s to handle a steady, predictable flow of federal capitalization grants, typically $2 to $3 billion per year combined across both programs. The BIL essentially tripled or quadrupled that annual flow overnight.

State SRF programs were not staffed, structured, or technologically equipped to process that volume. Many states have two to five full-time staff managing their entire DWSRF program. When you suddenly need to review, score, and execute three times as many project applications, the pipeline slows down.

The EPA has acknowledged this challenge and has provided supplemental technical assistance funding to states, but hiring and onboarding takes time. Several states told us informally that they did not reach full staffing for BIL processing until mid-2024 or later.

Lead Service Line Replacement: A Special Case

The BIL included $15 billion specifically for lead service line replacement (LSLR), driven by the updated Lead and Copper Rule Revisions (LCRR). This is the single largest line item in the water portion of the law, and it has its own deployment challenges.

Many utilities are still completing their mandatory lead service line inventories, which were due in October 2024 under the LCRR. Until a utility knows where its lead lines are, it cannot submit a credible project application for replacement funding. This has created a sequencing problem: the money is available, but the prerequisite data collection is still catching up.

Our data shows that LSLR-specific commitments account for roughly $5.1 billion of the $22.4 billion in total committed funds, about 34 percent of the $15 billion authorization. States with mature inventory programs, like Michigan and Illinois, are further ahead, while states that started their inventories later are still ramping up.

What This Means for Vendors

For companies selling into the water utility market, these findings have several practical implications.

Follow the funded projects, not just the need. The gap between authorization and disbursement means that a state with enormous infrastructure need but low disbursement rates is a weaker near-term market than a state with moderate need but high execution velocity. Vendors should track IUP project lists and SRF disbursement data, not just census data on aging pipes.

Anticipate a second wave. The roughly $20 billion in BIL funds that have been allotted but not yet committed represent a substantial wave of project activity that will hit the market over the next 18 to 24 months. States are catching up on administrative capacity, and the pipeline of approved projects is growing. Vendors who position now will be better placed when those projects move to procurement.

Small system aggregation is a real opportunity. Many of the states with the slowest disbursement rates have large numbers of small systems (serving fewer than 10,000 people) that lack the technical capacity to apply for SRF funding. Companies that can help aggregate demand, provide turnkey project management, or offer standardized treatment solutions for small systems are addressing a real market gap.

State-level relationships matter more than federal ones. Because the SRF is a state-administered program, the decision-makers who score projects, set funding priorities, and select eligible technologies are state employees. Understanding your target state's IUP scoring criteria, funding cycles, and priority lists is more actionable than tracking Congressional appropriations.

Our Ongoing Tracking

At United Current, we update our BIL funding tracker monthly, pulling from EPA allotment tables, state SRF annual reports, and USASpending.gov disbursement records. Our platform links funded projects directly to the utilities receiving them, so you can see not just that a state received $200 million, but that the Springfield Water Authority received a $4.2 million DWSRF loan for treatment plant upgrades, along with that project's timeline and scope.

The BIL remains the most significant market-shaping force in water infrastructure. But the headline number and the on-the-ground reality are two very different things. Understanding the gap between them is where the real intelligence lies.


Related Resources

United Current Team

Research & Intelligence, United Current

The United Current team combines deep water industry expertise with advanced data engineering to deliver actionable intelligence for companies selling into America's water infrastructure market.

Newsletter

Get insights like this every week.

Water infrastructure intelligence, funding updates, and market trends — delivered to your inbox.